Babangida Dajin
Bauchi Government reacts to Reps member represent Bauchi feaderal constituency in the house of representatives, Yakubu Shehu Abdullahi house building demolition says construction of building is violated government land policy
Bauchi state government has reacted to the development, through the special Adviser on media Mukhtar Gidado during a press conference on Monday at Government house Bauchi, says the construction of the building violated goverment policy of land administration.
According to the Media Aids, it become necessary for the state government to set the record straight and disabuse the minds of the public on any insinuation on the demolition saga.
He added, that on the 1st of October 2021, the state government demolished an ongoing illegal construction work of a house at Number 7 Buba Yaro road, belonging to a member of the federal house of representatives in the state due to factors which contravened the laws of government in connection to land.
“The government approved the sale of some of it’s residential houses to be sold to occupants on owner occupier basis, however government houses along Buba Yaro road old GRA Bauchi popularly referred to as Commissioners quarters are exempted from this policy.The said house at Buba Yaro road was allocated to the State House of Assembly to serve as guest house on the 23rd of June 2014”
“Inspite of the exemption of the houses along Buba Yaro road from the owner occupier policy of the state government, the then Commissioner for works, land and housing, under the first immediate administration of Alhaji Abubakar Tatari Ali, allocated the house to himself, using a fictious name of one Mohammed Kabir of Danjuma Goje street, Bauchi.The house was later sold to Yakubu Shehu Abdullahi, a member representing Bauchi local government at the house of representatives at the cost of N9 million” he said
The Special Adviser said that there was no record in the treasury or ministry of housing to show that the amount was paid into the government coffers, adding that the whole proceeds from the sale of the house, did not follow due process because the value of the house was not accessed by relevant government agencies and approval from the governor was not obtained.
He said that following the sale of the house, the state House of Assembly wrote to inform the state government on the 20th October 2019 about the development, after which the government requested Shehu Abdullahi to provide documentary evidence of the sale of the house to him, which uptil now, the lawmaker has not provided.
Mukhtar said that the state judiciary on the 17th of January 2021, officially wrote to inform the government that the house was used as a hide out for criminal elements that have been terrorizing residents of neighboring houses.
“Upon receiving the report of the state house of Assembly and the judiciary, government directed it’s relevant agencies to investigate the matter.In the course of the investigation, it was discovered that Honourable Yakubu Abdullahi had demolished the main building of the property and commenced construction of a new structure at the site”
“A notice of revocation was served on Yakubu Abdullahi on the 21st and 23rd September 2021 in respect to the certificate of occupancy fraudulently granted him by the then Commissioner of works, land and housing under the administration of Abubakar Tatari Ali, the revocation notice was duly acknowledged.
“Inspite of the revocation order, Yakubu Shehu Abdullahi continued with the Construction work at the site.Consequently, the state development board marked the building for stop work order on the 27th September 2021, which he refused to comply” The government added