Water scarcity in Bauchi will soon be a history as the rehabilitation and expansion of water facilities for Bauchi metropolis recorded 90% completion.

In an effort of the Bauchi State Urban Water and Sewerage Corporation (BSUWSC) through the Project implementation unit (PIU) of the Third National Urban Water Sector reform project (NUWSRP3) in ensuring quality and timely execution of the ongoing rehabilitation and expansion of water facilities for Bauchi metropolis, the Managing Director (MD) of BSUWSC and at the same time Project Coordinator (PC) of the (NUWSRP3) in person of Engr. Aminu Aliyu Gital alongside the project Staff and the management of BSUWSC have embarked on an intensive supervision of the entire project with a view to ensure that all contractor’s are working in line with the terms of reference (TOR) in order to meet with the project completion dateline of December 2020.

Engr. Aminu Aliyu Gital express delights with the quality and level at which the contracts are, and further appreciated and commented the good people of Bauchi metropolis for their patients and support towards making the entire project from design to reality. the MD pleaded for more patients,support and prayers from the general public towards the completion of the remaining 10% of the entire project.

1.Gubi Dam Rehabilitation Works.
Completed…………..100%
2. Rehabilitation of Conventional Water Treatment Plant
Completion level……….90%
3. Expansion of Conventional Water Treatment Plant
Completion level………90%
4. Construction of 1000/900mm Pumping Mains from conventional Water Treatment plant to Warinje Hills Reservoirs.
Completion level……….95%
5. Construction of about 7,000 cubic metre Concrete Reservoir at Buzaye Hill
Completion level……….99%
Rehabilitation of 2×11,000 cubic metre Concrete Reservoir at Warinje Hills.
Completion level………80%
6. Construction of 500mm Transmission Mains from Gubi Dam junction to Reservoir at Buzaye Hill.
Completion level………65%
7. Replacement of 50km Mains Distribution Network and installation of Bulk Meters-40(for Water production plants, Reservoirs and boundaries of distribution) (pressure and Billing)Zones.
Completion level……..90%
8.Extension of 100km Main Distribution Network.
Completion level………..95%
9).Construction of 4no Customer Care Centers.
Completion level……..100%
10). Construction of Gubi Dam Access Road.
Completion level…….. 70%
11).Total Renovation of Gubi Dam Staff Quarters.
Completion level……..98%
12).Total Renovation of BSUWSC Head quarters
Completion level……..98%
13). Additional Extension of 60km main Distribution Network.
Completion level…….at early stage.
Among other projects and consultancies that ongoing and some completed.
Engr. Aminu Aliyu Gital thanked His Excellency Sen. Bala Abdul Qadir Muhammad (Kaura Bauchi) for the his tireless efforts in ensuring that the Bauchi water project recorded 100% completion.
Sir this is a clear testimony that the good people of Bauchi state have made the right choice by giving you the mandate to pilot the affairs of Bauchi state for years to come insha Allah.

Our prayers is that may Allahu S.W.T grand you long live and good health to commission the Third National Urban Water Sector Reform Project under which these contracts were awarded upon completion.
Sir you will forever be remembered for bringing an end to Water supply scarcity In Bauchi State.